Tingo Maria Airport runway work expected to finish in late November

Written by AI from 1 report listed below. Not checked by a person before publication. How we use AI
Governor Antonio Pulgar said the runway at Tingo Maria Airport is expected to be completed by the second half of November, coinciding with the town's anniversary.
The project, which is about 65% finished, involves repairing more than 2.4 kilometres of runway at a width of 30 metres; an extra pneumatic roller and night shifts starting around 20 October have been added to speed progress, and the budget has risen from an initial S/ 17.4 million to roughly S/ 20 million. The Dirección General de Aeronáutica Civil must evaluate the runway before commercial operations can resume, while CORPAC is handling protection of the final segment near the river.