Long Thanh Airport conducts three-phase ORAT tests with 55 scenarios

Written by AI from 1 report listed below. Not checked by a person before publication. How we use AI
Long Thanh Airport is carrying out three full‑scale Operational Readiness and Airport Transfer (ORAT) tests, with phase 1 scheduled for September‑October, phase 2 for November and phase 3 for December.
ACV and Incheon Airport consultants have created 55 operational scenarios covering passenger service and connectivity, baggage handling, airfield operations, and security, safety and IT, including a fuel leak during refuelling, a medical emergency and a passenger from a disease‑affected area; Vietnam Airlines is preparing technical service, maintenance, catering and ground service, while four of the 16 main contracts are completed, eight are on schedule and four remain pending.