Long Thành airport to begin operations in December after three trial phases
Based on · First reported
Sources

- Three trial phases are scheduled for September‑October, November and December, each covering passenger service and connectivity, baggage handling, runway operation, security, safety and IT at Long Thành airport.
- Component 3 of the project comprises 16 contracts worth 73.9 trillion VND, about 86% of the total contract value; four contracts have been completed, eight are on schedule, and four runway‑related contracts for the passenger terminal, internal transport and technical infrastructure, cargo terminal 1 and a parking lot remain pending. The airport aims to start operations in December, with legal and operational documents to be reviewed and approved in October and November, and progress reported at roughly 80% by the deputy prime minister.